Minister of Power & Energy Kanchana Wijesekera says 10 of the 33 coal cargos required for the Norochcholai Coal Power Plant have been unloaded thus far.

Meanwhile, two more cargos are scheduled to arrive before the end of January and seven cargos each in February, March and April.

Taking to his Twitter handle, the lawmaker noted that insufficient cash flow and delays in financing have made it challenging to secure cargo on time and are delaying the process.

In a separate tweet, Minister Wijesekera revealed that 42.58 GWh of energy in total was generated on Monday (Jan 23), while 2.22 GWh of energy was saved from scheduled power cuts.

As per the power generation summary, the CEB has generated 47.03% of energy using coal, 28.17% using hydropower, 10.95% through thermal power, and 0.85 % from wind power, while independent power producers generated 4.94% using solar power and 1.64% using wind power.

Disclaimer: All the comments will be moderated by the AD editorial. Abstain from posting comments that are obscene, defamatory or slanderous. Please avoid outside hyperlinks inside the comment and avoid typing all capitalized comments. Help us delete comments that do not follow these guidelines by flagging them(mouse over a comment and click the flag icon on the right side). Do use these forums to voice your opinions and create healthy discourse.

Most Viewed Video Stories

Amendment to Press Council Act not an attempt to suppress social media - Cabinet Spokesman (English)

Amendment to Press Council Act not an attempt to suppress social media - Cabinet Spokesman (English)

Cabinet greenlights Rs. 750M allocation for first stage of Dambulla Industrial Park (English)

Sri Lanka needs thinkers who question, create, and innovate – PM Harini (English)

Sampath Manamperi an ex-cop and suspect in Raviraj murder – Cabinet Spokesman (English)

🔴LIVE | Ada Derana Prime Time News Bulletin

CEB workers threaten to intensify trade union action if demands are not met (English)

Another stock of chemicals used in manufacturing ‘Ice’ found in Kandana (English)