Water leakage in Uma Oya project decreased

Water leakage in Uma Oya project decreased

October 23, 2017   09:14 am

The amount of water being drained to the main tunnel of the Uma Oya project is currently decreasing, information revealed.

This was revealed following a discussion held regarding Uma Oya project recently.

Earlier, the main tunnel leaked about 1460 liters of water per second, and now it has been reduced to a range of 550 - 650 liters per second, according to engineers.

The engineers have also said that the water leakage was reduced due to the current construction.

The amount of water leakage could be further reduced during the next 3 months, the engineers pointed out.

Meanwhile, a large number of dried-up wells that were in Bandarawela area have been re- filled with water, discussions revealed.

 

Disclaimer: All the comments will be moderated by the AD editorial. Abstain from posting comments that are obscene, defamatory or slanderous. Please avoid outside hyperlinks inside the comment and avoid typing all capitalized comments. Help us delete comments that do not follow these guidelines by flagging them(mouse over a comment and click the flag icon on the right side). Do use these forums to voice your opinions and create healthy discourse.

Most Viewed Video Stories

SC reviews recovery of excise duty arrears from defaulting liquor manufacturers (English)

SC reviews recovery of excise duty arrears from defaulting liquor manufacturers (English)

Digital education policy to be introduced in April – PM Harini (English)

Deputy Minsiter Sunil Watagala rejects allegations made by Ven. Kassapa Thero (English)

🔴LIVE | Ada Derana Prime Time News Bulletin | 2026-02-13

🔴LIVE | Ada Derana Midday Prime News Bulletin | 2026.02.13

Nimal Siripala claims new law may drive Sri Lanka towards a 'dictatorship' (English)

Fishermen continue 'Satyagraha' for eighth day over seine fishing ban (English)

GMOA assures no strike, pledges commitment to public wellbeing (English)