Second generator at Norochcholai plant to be added to national grid

Second generator at Norochcholai plant to be added to national grid

October 23, 2022   06:57 pm

The second generator at the Norochcholai Coal Power Plant, which had been shut down due to maintenance activities, has now been restored and will be reconnected to the national grid today (Oct 23), an official said.

The President of the Engineers’ Association of Ceylon Electricity Board (CEB), Nihal Weeraratne stated that the maintenance work of the power plant has now been completed.

Accordingly, the electricity capacity of 270 Mega Watts generated by the power plant will be gradually added to the national grid.

After reconnecting the second generator to the system, the third generator of the Norochcholai power plant is scheduled to be shut down for maintenance work as well.

Disclaimer: All the comments will be moderated by the AD editorial. Abstain from posting comments that are obscene, defamatory or slanderous. Please avoid outside hyperlinks inside the comment and avoid typing all capitalized comments. Help us delete comments that do not follow these guidelines by flagging them(mouse over a comment and click the flag icon on the right side). Do use these forums to voice your opinions and create healthy discourse.

Most Viewed Video Stories

LIVE🔴 Ada Derana Prime Time News Bulletin 6.55 pm

LIVE🔴 Ada Derana Prime Time News Bulletin 6.55 pm

Ex-President Ranil made statement backing Chamara Sampath following a request by MP's wife – court told

Sri Lanka's new direction must be communicated to the world - President tells new diplomats (English)

SLPP decides not to attend opposition parties' discussion on LG bodies (English)

Gerandi Ella tragedy: DMT officials inspect bus at Kotmale Police (English)

1 in 3 adults have high blood pressure; 50% unaware of condition – Health officials

LIVE🔴 Ada Derana Prime Time News Bulletin 6.55 pm

LIVE🔴 Ada Derana Lunch Time News Bulletin 12.00 pm